Verified record
Conneely Excavation's most recent documented job put its crew on a Wellesley condominium project — in a June 2024 site-progress report, they backfilled the foundation wall to 5 feet and installed the project's phase-two perimeter drain. BuildZoom's page for the company samples six 2018 excavation, sewer and water permits filed across Roslindale, Brighton, West Roxbury, Jamaica Plain, Charlestown and South Boston, all under a Massachusetts construction supervisor license number tied to Padraig Conneely. That license number is only BuildZoom's own listing, not something confirmed against the state registry, so it's worth checking current status directly with the licensing board before hiring. Get a written scope for the excavation and drainage work, confirm insurance, and ask for references from a job similar in size to yours.
“3 week look ahead 6/10 — The Albion, Wellesley MA ... # 3 week look ahead 6/10 ... Pittol concrete: continue top of wall embeds, should complete 6/11/24.Conneely excavating : back fill phase #2 foundation wall up 5’-0” / install perimeter drain phase #2 / start excavating for underground plumbing 6/11/24White cap : deliver wire mesh ,chairs ,slab dowels for SOG 6/12/24 Joyce Plumbing : to deliver materials for underground plumbing 6/14/246/17/24 : ... Conneely finish prepping underground excavation at west end/phase #2 w/ sand, prep areas for retaining walls/north,storm system, backfill underg”
Specializes in
Also offers
Languages
1 change recorded — last scanned Sep 19, 2026.
Wood and block retaining walls4.9
Bulkhead replacement4.8
Load-bearing wall opened with an LVL beam4.3